6 April
Module 4/6 has landed on the ways. Note the
spacer beams that AMI has installed between the hulls to ensure that spacing is
maintained during assembly.
23 March
The foot valve and hull penetration for the HPR
418 are fitted into the pump room. The 418 will be set atop the valve, after the
production welding is complete.
16 March
After AMI installed the last side shell on Module 4-6, they put a canvas cover
over the pump and sonar room, which was promptly ripped off by a storm that
passed over the area the next day.
The pump room has a lot of equipment and piping left to install before it is
ready to go to the paint shop. We are also having a problem with keeping the
area and piping clean.
9 March
The inserts in the base-plate for the EM 500. AMI has not cut the opening for
the ADCP as of Friday.
2 March
The last frames have been installed on modules 4 and 6.
Hanging the first side-shell on module 4 and 6.
25 February
Continue to assemble frames into module 4 and 6,
which are being worked together.
The sonar frame boxes have not been installed at
this time. (As of Fri. p.m.)
20 February
Module 6 is joined to module 4 to complete assembly as a joined unit..
16 February
The leveling pins for the sonar frame.
Starting to fit the sonar frame into box that is part of the foundation for the
module
4/6/01