5 May
Main motor landed and power for heaters installed.
27 April
The starboard main motor has landed.
The main motor forward foundation.
20 April
The main motors are being reassembled in the
yard, in preparation for landing.
13 April
The foundation framing in motor room #1 is being painted prior to landing the
motor.
The main motor assemblies are starting to arrive
in yard.
23 March
AMI is using a calibrated load cell to ensure that their installed system is
accurate.
Module 5 is being moved to the building/ launch ways.
Module is made up to #3 on the building ways. By moving this module out of the
assembly area, it has freed up a lot of space. You can also see the ship
starting to take shape.
9 March
The foundation has been modified to fix the loading problem of the pumps,which
you can see in the picture below.
2 March
This is a pump installed in the pump room. Note that even without liquid in the
pump end, the the forward mounts are almost bottomed out.
This pump is in the pump room and has the same problem with mounts not properly
loaded.
20 February
Outfitting continues in the pump room.
16 February
This area will be the pump room. Outfitting is starting, and the last piece of
shell goes on after shop work is complete.
12 February
Side shells are going onto the module.
9 February
Base for main motor in module 5
6 February
Starting to assemble motor foundation, Capt. Coste is in picture.
5/5/01