16 February 2001
The piping in the module has been replaced to meet the material requirements.
31 JANUARY 2001
Module 3 moved into final assembly area, and being prepared for ABS inspections.
27 JANUARY 2001
Piping and ladders installed as part of outfitting.
23 JANUARY 2001
A long range shot of module 3. It is about as big
as can be fitted in bay 1
The stiffeners are installed on side shell prior
to being fitted up to frames
Note the cuts in the frames in preparation for
pipe runs, and the size of the keel beams
A cut in the keel plate in preparation for
installation of transducer tube
The side shell in a welding gig prior to fitting
up to frames on module 3
19 JANUARY 2001
The keel and base plate for module 3 are being
assembled in the shop.
The vertical frames for module 3 are being
assembled. Steve Madden is the person in this picture.
Each part that is cut is also marked off the NC
tape to insure that it can be tracked.
Stiffeners are added on the plate line
Return to 3rd Platform
Return to this Home page