9 November

314Mod1-plat.jpg (55187 bytes)

28 September

272Mod1cannard.jpg (63220 bytes)

19 May

138mod1a.jpg (59722 bytes) 138Mod1d.jpg (57962 bytes) Module 1 is landed on the building ways.

12 May

132Prep for mod1.jpg (45974 bytes) Preparations have been made to land module 1 on the ways. This module should land next this coming week.

5 May

124mod1.jpg (94235 bytes) Work continues in preparation to move this module to the ways.

20 April

110Mod1b.jpg (82581 bytes) 110Mod1d.jpg (71724 bytes) Module 1 is taking shape nicely. The inlet for the bow thruster is the opening you see in the side.

 

13 April

103Mod1Ab.jpg (90200 bytes) 110Mod1Thruster.jpg (73281 bytes)  The shaped sections on this module are turning out well. The making of these shapes is quite an art if done freehand.

6 April

96BowThrusFitup.jpg (60549 bytes) The first trial fit-up of the bow thruster was made this week.

96Mod1BowB.jpg (93923 bytes) The bow shapes and cap are being installed on module 1.

30 March

89mod1.jpg (77081 bytes) 89mod1B.jpg (86941 bytes) The foundation for the bow-thruster is being prepared for landing the unit.

23 March

82mod1.jpg (76228 bytes) Shop assembly has started in the shop for the last module in the lower hulls.

9 March

68Bow Thrusgear.jpg (71160 bytes) The bow thruster with the turning gear and bottom plate visible. The person in the picture is Shawn Izenson.