18 July Module 19 port
17 July
14 June - Module 12-14 landed
12 June - Module 12-14 turned over
9 June
2 June
Assembly continues on module 12
Assembly of module 19 port started this week.
26 May
21 May
On Monday module 16-18 was landed, and fit-up
commenced.
19 May
Module 16-18 is turned over to complete welding
prior to landing.
Module 14 continues in preparation for joining to
module 12 prior to landing.
12 May
Assembly of module 16-18 continues. Besides
piping, ventilation is also being added during field assembly.
27 April
Module 16, the first unit on the port side column, is in the assembly process.
7/22/01