HOT-89: Chief Scientist Report


Chief Scientist: L. TUPAS


Hawaii Ocean Time-series
HOT-89  Chief Scientist's Report


Loading: January 8, 1998		Chief Scientist: Dr. Louie Tupas
Departed: January 9, 1998 at 0900	Master: Captain John Stahl
Returned: June 13, 1998 at 0000		Deck Operations: Mr. Dave Gravett
Vessel: R/V Moana Wave			Electronics Technician: Ms. Sharon Stahl

1.	SCIENCE PERSONNEL

	Luis Tupas - UH, JGOFS
	Dale Hebel - UH, JGOFS
	Ursula Magaard - UH, JGOFS
	Lance Fujieki - UH, JGOFS
	Pat Driscoll - UH, JGOFS
	Karen Selph - UH, JGOFS
	Dan Sadler - UH, JGOFS
	Hans Ramm - UH, WOCE
	Craig Nosse - UH, WOCE
	Don Wright - UH, WOCE
	Fernando Santiago Mandujano - UH, WOCE
	Mark Valenciao - UH WOCE
	Mai Lopez - SIO
	Markus Karner - UH, Post-Doc
	Craig Motell - UH, Technican
	Kyle Margenau - HPU, Undergrad
	Donna Robinson - HPU, Undergrad

2.	GENERAL SUMMARY

	All objectives of the JGOFS and WOCE programs were accomplished. All
planned stations were occupied. All core samples were taken and the 36
hour CTD burst sampling period was not interrupted. All samples for
ancillary projects were taken. Floating sediment trap array and primary
production array deployed and recovered successfully. No samples were
lost during the in-situ incubations. ADCP measurements were made
throughout the cruise. The pCO2 system was operated using the ships
uncontaminated seawater intake system. The optical plankton counter did
not function despite several attempts to troubleshoot and repair the
instrument. OPC work was abandoned and the schedule of work moved up by
about 6 hours. Transit to Snug began at about 1600 on 12 January and
cruising speed was increased to arrive at Snug by 0000 on 13 January.
Unloading commenced after early breakfast.

3.	R/V MOANA WAVE, OFFICERS AND CREW, TECHNICAL SUPPORT

	The R/V Moana Wave continues to maintain the excellent ship support for
our work. The officers and crew were most helpful and accommodating.
They showed enthusiasm and concern for our work and were very flexible
in receiving changes in our operational schedule. Technical support
during this cruise was excellent. STAG personnel were available at any
time to assist in our work and made things much easier for us.    
        	
4.	DAILY REPORT OF ACTIVITIES

January 8, 1998; Loading Day
 
	All deck and lab equipment were moved from either SNUG Harbor labs or
UH on this day. All electrical and electronic connections were made for
the CTD and the OPC. All lab equipment were stowed away and secured. All
laboratory instruments were tested and appeared functioning. No problems
were encountered.

January 9, 1998
	
	Scientists arrived on ship by 0830. Ship departed at 0900 after all
scientists and equipment arrived. Fire and emergency drills conducted at
0930 followed by a safety briefing by the first mate and a short science
meeting. Arrived at Station Kahe at 1200. Conducted weight cast followed
by a light cast using the Profiling Reflectance Refractometer (PRR) and
the Tethered Spectral Radiometric Buoy (TSRB). A 1000 m CTD cast
completed the operations. Started transit to Station ALOHA at 1600
following a depth contour of about 500 meters for ADCP bottom tracking.
Uncontaminated seawater system was run and the pCO2 system was connected
and operated. Transit to Station ALOHA and arrived at 0000. A net tow
was made upon arrival at Station ALOHA.  

January 10, 1998

	Floating sediment trap array deployment began at 0100 and accomplished
at 0200. Twelve traps were deployed at 150 meters. 3 traps were deployed
at 165 meters. After deployment, the ship transited to center of station
and commenced the WOCE deep cast at 0230. Cast was completed at 0600.
CTD burst sampling commenced at 0800 and maintained at 3 hour intervals.
Zooplankton tows at noon successful. PRR and TSRB cast was made during
the SeaWiFS flyover time. 

January 11, 1998

	CTD casts continued at 3 hour intervals. Go-Flo cast conducted at 0130.
Primary production array deployment commenced at 0500. CTD casts
continued at 0520 continuing at 3 hour intervals. Zooplankton tows
conducted at noon. PRR cast at 1230. Retrieval of primary production
array commenced at 1900. No samples were lost. CTD casts continued at 3
hour intervals. Last 1000 meter cast conducted at 2000. Transit outside
the circle to pump tanks at 2130 and return for OPC towing at 2200.

January 12, 1998

	OPC instruments not functioning despite several attempts to trouble
shoot. Towing aborted at 0800 and began transit to sediment trap
retrieval site. Retrieval started at 0900, completed at 1100. All
sediment traps were retrieved undamaged and the whole array was safely
and successfully retrieved. Transit to HALE ALOHA. Cast started at 1300
and completed at 1430. Transit to Honolulu at 1500. 

January  13, 1998

	Arrived at Snug Harbor at 0000. Unloading commenced at 0700, completed
at 1100.


SAMPLES TAKEN FOR OTHER INVESTIGATORS

1. DIC water samples for C.D. Keeling, SIO-UCSD
2. DIC water samples for P. Quay, UW
3. Particulate samples for Jon Zehr, RPI
4. Seawater for E. Laws, UH


Return to Cruise Summaries. (Tables)

Return to Cruise Summaries. (No tables)

Last modified: September 17, 1998