![]() |
| ||
|
HOT-216 Day 1 Report Operations continue as planned at Station ALOHA with some slight delays due to the longer than anticipated transit time to ALOHA as result of the large northerly swell. The primary production CTD cast scheduled to go to 1000 m was shortened to 200 m to allow for the primary production array to be deployed on time. One of the ship's two generators was malfunctioning on the morning of 3rd Nov. The ship's engineers managed to resolve the problem. Eight CTD casts have been conducted at ALOHA including one deep cast. The sediment traps array was deployed successfully upon arrival at ALOHA. The primary production array was deployed and recovered without problems. The ATE sampler was deployed but on retrieval was found not to have functioned correctly. Sea conditions at ALOHA are very confused with two swells present. One large swell 6-8ft from the northwest and another smaller trade wind swell from the east is making the ride uncomfortable. Winds are 20-25 knots from the east. Schedule of Activities 02 November 2009 03 November 2009 Paul Lethaby HOT-216 Day 2 Report Operations continue as scheduled at Station Aloha. The second deep cast has just been completed marking the end of the 36 hour burst sampling period. A total of 16 CTD casts have been completed at Station ALOHA including 2 deep casts. The gas array was deployed successfully early this morning. There were some problems with the AC9 just before it was due to go in the water but it was fixed in time for it to be deployed. The hyperpro cast did not reach sufficient depth and had to be redone. Filters from 150 m and 175 m depths on the PPO4 and PC/PN casts showed signs of a thick browny-red waxy substance on them. Filtering times were much longer (~12h). The north-west swell continues at 6-8 ft with 4-5 ft seas from the north east. Winds calmed this morning to 15 knots but have built back up over the course of the day to 20-25 knots. Schedule of activities 04 November 2009
HOT-216 Day 3 Report Operations are now complete at Station ALOHA. The sediment traps array, the gas array, and the sea glider were all recovered this morning sucessfully. The deep moored thermistor chain was ranged upon and and response was received. One AC9/Frrf/LISST cast, and two Hyperpro Optics casts were conducted. Two CTD casts were conducted near the WHOTS mooring (Station 52), one to 200 m and one one hour yo-yo to 200 m. The near bottom cast at Kaena has just been completed and we are now transitting to Snug Harbour. Winds are 15 - 20 knots from the east with seas and swell reduced from yesterday. Schedule of activities 05 November 2009 06 November 2009 Paul Lethaby |
|||