Time Line Page

 

Phase I 

Design and construct a proof of concept module to be deployed in 2007

Outcome: Hydrophone amplifier, A/D converter, Manchester encoder, and microprocessor completed and under testing phase. 

 

Task Timetable

 

Task

Date Completed

   

Test Proof Module on Hawaii 4 cable

12/13/07 to 12/14/06

   

Wet test of Proof Module at Makai Pier

1/11/07 to 1/12/07

   
Temperature Cycle Proof Module 1/15/07 to 2/2/07
   
Prepare for Deployment 2/5/07 to 2/9/07
   
Hawaii4 Cable Cut 2/12/07
   
Splice Cable Termination 2/15/07
   
Deployment of Proof Module Operational 2/16/07 3:00am
   
   

 

 

Design and construction of a prototype Observatory.

Outcome: Completed 6/04.

 

Calibration and testing of Observatory hardware and software to control power and communications. Integrate Observatory to simulated experiment.

Outcome: Completed system integration of Observatory with the SEM (Small Experiment Module) and ULF.  Able to supply and control power to the SEM, and transmit leveling instructions to the ULF and receive simulated seismic data. 7/04

 

Phase II

        Construction of Observatory components.

 

Task Timetable

 

Task

Date Completed

   
Complete assembly of observatory electronics Completed 6/07
   
Cold testing of observatory electronics Completed 9/08
   
Mechanical Fabrication Estimated completion 10/08
   
System integration testing Completed 9/07
   
Observatory deployment (Cruise Date) 10/17/08 - 10/28/08
   
   
   
   

 

Page Last Modified 09/24/2008

 

 

This site maintained by Bill Doi
Copyright © 2004  [SOEST/ESF]. All rights reserved.

The ALOHA Cabled Observatory is funded by the National Science Foundation

Revised: September 19, 2008