Time Line Page
Phase
I
Design and construct a proof of
concept module to be deployed in 2007
Outcome: Hydrophone amplifier, A/D
converter, Manchester encoder, and microprocessor completed and under testing
phase.
Task
Timetable
|
Task |
Date Completed |
| |
|
|
Test Proof Module on Hawaii 4 cable |
12/13/07 to 12/14/06 |
| |
|
|
Wet test of Proof Module at Makai Pier |
1/11/07 to 1/12/07 |
| |
|
| Temperature Cycle Proof
Module |
1/15/07 to 2/2/07 |
| |
|
| Prepare for Deployment |
2/5/07 to 2/9/07 |
| |
|
| Hawaii4 Cable Cut |
2/12/07 |
| |
|
| Splice Cable Termination |
2/15/07 |
| |
|
| Deployment of Proof Module |
Operational 2/16/07 3:00am |
| |
|
| |
|
Design and construction of a
prototype Observatory.
Outcome: Completed 6/04.
Calibration and testing of Observatory hardware
and software to control power and communications. Integrate Observatory to
simulated experiment.
Outcome: Completed system integration of
Observatory with the SEM (Small Experiment Module) and ULF. Able to
supply and control power to the SEM, and transmit leveling instructions to the
ULF and receive simulated seismic data. 7/04
Phase
II
Construction of
Observatory components.
Task Timetable
|
Task |
Date Completed |
| |
|
|
Complete assembly of observatory electronics |
Completed 6/07 |
| |
|
| Cold testing of observatory
electronics |
Completed 9/08 |
| |
|
| Mechanical Fabrication |
Estimated completion 10/08 |
| |
|
| System integration testing |
Completed 9/07 |
| |
|
| Observatory deployment
(Cruise Date) |
10/17/08 - 10/28/08 |
| |
|
| |
|
| |
|
|
|
|
Page Last Modified
09/24/2008
|